ADU Builder in Foster City
Foster City is the most demanding place on the Peninsula to put a foundation in a backyard, and its own building code says so. Here is what the city actually requires, what it costs, and why a soils report comes before anything else.
Why an ADU in Foster City starts underground
Most Peninsula cities let you design an ADU and deal with the ground later. Foster City does not, and the reason is written into its own findings of fact. The city adopted local amendments to the California building code specifically because of what it is built on.
The city is built on dredged fill
Foster City describes itself, in Ordinance No. 655, as a manmade island developed over former marshland. In the early 1960s hydraulic fill of sand and clam shells was dredged from the Bay and laid to an average depth of five feet over the existing land. That is the ground your ADU sits on.
Bay mud up to 30 feet thick
Beneath the fill, the city records unconsolidated fine silty clay varying from a few feet to as much as thirty feet deep, with bedrock generally three hundred feet or more down. The city's own finding is that the weight of the fill compacts the younger bay mud underneath, and that this compaction must be accounted for in the design of structures and drainage.
Seismic Design Category E, 1,200 psf
Foster City publishes a presumptive soil bearing value of 1,200 psf and notes that anything more requires a soils or geology report. Its seismic design category is E, the most severe normally encountered in residential work, and the city places itself in Seismic Site Class D, E or F.
Soil that attacks metal
The city's findings state plainly that the salt and mineral content of the fill is very destructive to metal in contact with the soil, with chloride concentration in the highly to very highly corrosive range and adverse sulfate content. The building code amendments require a geotechnical report to recommend protection for steel and concrete against long-term deterioration from contact with on-site soils.
The code assumes your building will settle
The clearest signal of all sits in the city's roof drainage amendment. Roofs must be designed against ponding after long-term deflection and possible differential foundation subsidence, with a minimum assumed ponding of one eighth of an inch for every foot of the building's minimum dimension. On a twenty-foot-wide ADU that is two and a half inches of assumed sag, designed in from day one.
One claim you will see repeated online is that Foster City requires piles for an ADU. It does not. The code requires that a geotechnical engineer determine the foundation type and that the foundation be engineered to their report. Anyone quoting you a pile foundation before a soils report exists is guessing.
What Foster City actually allows
Governed by Foster City Municipal Code Chapter 17.78, most recently amended by Ordinance No. 692 in August 2025. Where the city's published handbook and the code disagree, the code controls.
| Unit type | Maximum size | Height | Setbacks |
|---|---|---|---|
| Junior ADU (JADU) | 500 sq ft, within the existing walls | n/a | n/a |
| Attached ADU | 1,200 sq ft or 50% of the primary dwelling, whichever is less | 25 ft or the primary dwelling's limit, whichever is lower, max 2 stories | 4 ft side and rear |
| Detached ADU | 1,200 sq ft or 50% of the primary dwelling, whichever is less | 16 ft, or 18 ft within half a mile of a major transit stop, plus 2 ft to match the main roof pitch | 4 ft side and rear |
| Conversion ADU | No size cap within existing space, plus up to 150 sq ft for ingress and egress | Existing | Existing |
- The code guarantees you at least an 800 sq ft ADU at 16 ft with 4 ft setbacks, whatever the other standards would otherwise preclude. The city's own handbook says 850 sq ft in several places; the code says 800, and the code governs.
- ADUs are not permitted in the front yard unless an 850 sq ft unit is genuinely infeasible in the side and rear yards.
- R-1 lot coverage is capped at 50%, and the city requires a lot coverage diagram showing the ADU, the house and any accessory structure taller than the fence line. Structures over six feet count; unroofed decks and balconies do not.
- Parking is capped at one space per unit or per bedroom, whichever is fewer, and there are eight exemptions including proximity to transit, studios, JADUs, and demolishing a garage to build the ADU. The historic-area exemption exists in the code but the city notes no historically significant areas exist in Foster City.
- Owner occupancy is not required for an ADU. Foster City's code still requires it for a JADU, along with a recorded deed restriction, but state law narrowed that on 1 January 2026 so it applies only where the JADU shares sanitation facilities with the main house. The city code predates the change, so confirm which governs your project before you rely on it.
Foster City rules that go beyond state law
State ADU law sets a floor, not a ceiling. Foster City adds design requirements that catch owners out when they arrive with plans drawn for a generic California lot.
Match the house
Attached, detached and conversion ADUs must use the same exterior wall and roof colors as the primary dwelling. Attached units and JADUs must match its roof pitch and eave detail within 2:12.
Anything on a second floor is restricted
Upper windows facing a neighbor within ten feet of the line must be obscured, offset or splayed, and balconies, decks and roof terraces facing another residence are prohibited outright on new construction. Worth knowing before anyone draws a roof deck.
You must notify the neighbors
A courtesy neighbor notification report is a required application item: adjacent owners have to be told about the new ADU. Garage conversions are exempt from this one.
38 neighborhood design prototypes
Foster City's Planning Division maintains design prototypes for 38 named communities, from Shell Cove and Sea Colony to Nantucket Cove and Treasure Isle, and many of them cover accessory structures specifically. Check the prototype for your neighborhood alongside any recorded CC&Rs before design starts.
PG&E sign-off is a completeness item
Your application is not complete without a PG&E letter confirming the existing service can carry the new ADU load, or details for a new approved service. That is a lead-time item, not a formality.
No separate sale
Foster City has not adopted an AB 1033 ordinance, so an ADU here cannot be sold separately as a condominium. The only separate-conveyance route in the code is a narrow provision for qualifying nonprofit-built housing.
What Foster City charges
Figures below are from the adopted Master Fees and Service Charges Schedule for FY2026-27. The city's own ADU handbook still quotes the superseded numbers, so check the fee schedule rather than the handbook.
- Parks facilities impact fee
- $15,406
- Public safety impact fee
- $1,645
- Transportation impact fee
- $2,191
- Total impact fees per full dwelling unit
- $19,242
- Plan check
- 70% of the building permit fee
- General plan maintenance fee for ADUs
- No fee
- An ADU of 750 sq ft or less is fully exempt from impact fees. Above 750 sq ft, impact fees are charged in proportion to the ADU's size relative to the primary dwelling, so a 1,000 sq ft ADU beside a 2,000 sq ft house pays roughly half.
- The first plan check is included and the second costs nothing extra. Third and subsequent reviews are charged at actual cost, which is a direct argument for getting the first submittal right.
- The express plan check surcharge does not apply to ADUs. The city exempts them by name.
- Impact fees are adjusted every year by the construction cost index, so confirm current figures before you budget.
- Water and sewer connection charges are listed in the fee schedule for dwelling units generally, but the schedule does not state how they apply to an ADU. This is a potential five-figure swing and we confirm it with the Building Division for your specific project rather than guessing.
How long Foster City takes
Foster City publishes its review clocks, which is more than most cities do. The clocks only start once your application is complete, and completeness is where most projects lose time.
- 15 business days
Completeness review
Before any clock starts, the city checks you have supplied every required document. The engineered foundation plan designed to a geotechnical soils report is on that list, in bold. Without it you are not in the queue.
- 30 days
Pre-reviewed plans
Using a plan the city has already pre-approved cuts the review to thirty days. Foster City offers four GLADUR pre-reviewed ADU designs free to download, run with HEART of San Mateo County, plus its own pre-approval program.
- 60 days
Standard ministerial review
A complete standard ADU application gets a ministerial decision within sixty days. If the ADU is part of a new or remodelled primary residence, that clock does not start until the house itself is permitted.
- Varies
Correction cycles
Plans are resubmitted until they meet city and state code, and the city publishes no cap on the number of cycles. The first two plan checks are covered by your fee; from the third you pay actual cost. This is where a complete first submittal pays for itself.
Overlay
The levee, and what flood zone means for your foundation
Foster City sits behind a levee, and its flood designation has been in flux. Here is where it genuinely stands, including the part nobody can currently answer.
The levee was rebuilt and finished in 2024
FEMA found in 2014 that the levee did not meet its criteria. Voters passed Measure P in 2018 with about 81% support, authorising a $90 million bond. Construction ran from autumn 2020 to final completion in February 2024, designed to protect against three feet of sea level rise through 2100.
The remapping is unresolved
The city submitted a Letter of Map Revision to FEMA in February 2024 based on the as-built levee, and said the process could take six months to a year or more. Every public source goes quiet after that, and the city's own levee page still describes the completed project in the future tense. We check the effective flood map for your specific address rather than repeating a designation that may be out of date.
If your parcel is in a flood hazard area, it changes the foundation
Foster City requires residential construction in a mapped special flood hazard area to have its lowest floor two feet above base flood elevation. That is a foot more freeboard than the federal minimum, and it pushes an ADU onto a raised or stem-wall foundation. After construction the elevation must be certified by a civil engineer or licensed surveyor.
An ADU does not get the shed exemption
Detached garages and storage structures can sit below base flood elevation with flood vents and resistant materials. An ADU is habitable space, so it does not qualify for that allowance and is treated as residential construction.
What Foster City does not have: fire hazard zoning
San Mateo Consolidated Fire confirms Foster City is not located within a fire hazard severity zone. That is a real advantage over the hill cities on this side of the county. Belmont carries 971 acres of moderate zone and Millbrae was remapped in 2025 from none to 353 acres of very high, and both now face wildland-urban interface construction standards that simply do not apply here.
Flood zone is parcel-specific and it is the single largest unknown in a Foster City ADU budget. It is the first thing we check, before any design work.
Where else we build
Testimonials & Reviews
Real reviews from Bay Area homeowners we’ve built for.
“I am so happy to find ADU San Mateo. The crew are nice, professional, doing a great job while pay attention to details, all with a good price. Highly recommend!”
“Finished work in a timely fashion. Quick to respond.”
“Excellent service highly recommended”
“ADU San Mateo went above and beyond our expectations. They were with us every step of the project, making the experience easy and headache free. ADU San Mateo has great attention to detail and abundance of carpentry knowledge. They always answered our calls and ensured the job site was clean and safe before ending the workday. The team was very professional, clean, and respectful. We contracted ADU San Mateo to build our ADU unit and cannot be happier with the outcome. Would definitely recommend to anyone looking for cost-effective get it right the first time company. Definitely would use for our future projects.”
“Dependable, responsive, quality workmanship and dedication to getting the project completed timely and on or under budget. They treated our home as if it was their own. The outcome exceeded my expectations. Would recommend to my friends and family.”
“I would highly recommend ADU San Mateo to all my friends and family. The crew is efficient, polite and hardworking. They are easy to work with and very competitive with pricing. We would definitely recommend and hire again for future projects.”
“Such exceptional work done, I am beyond pleased with the results! Paid close attention to detail and I was always kept informed. High quality work and excellent service gave us the results we expected. I was completely impressed with their professionalism and customer service. I highly recommend this business!”
“I HIGHLY recommend Eli and his team for any home remodeling projects. They did my staircase and completely did what I have envisioned. I am a perfectionist, so I am glad I met them. They are very detailed oriented, very punctual, and there were no delays. He advised me what’s the best route, up to code, and provided recommendations tweaks on my design. I provided a 3D rough draft sketch to them, the measurements were 100% accurate. I can guarantee you that you won’t be disappointed, as I went through roughly 10 contractors and FINALLY found the right team. I am looking forward to seeing how my kitchen tiles turn out.”
“They were responsive and efficient and easy to work with.”
Foster City ADU questions
Here are some common questions along with their answers to help clear up any confusion.
Still have a questions?
Let’s discuss your goals and find the best ADU solution for your property.
Get a free ConsultationDo I really need a soils report for an ADU in Foster City?
How big an ADU can I build in Foster City?
Will I lose my parking if I convert the garage?
What will the permit fees actually be?
How long does the whole thing take?
Can I sell the ADU separately later?
Where these figures come from
Every rule and fee on this page is taken from Foster City’s own published code and fee schedule. Ordinances change, so confirm anything you are budgeting against.
- Foster City Municipal Code Chapter 17.78, Accessory Dwelling Units
- City of Foster City, Accessory Dwelling Unit (ADU)
- Foster City adopted codes and local design criteria
- Foster City Master Fees and Service Charges Schedule FY2026-27
- GLADUR pre-reviewed ADU plans
- Foster City Levee Improvements Project
- San Mateo Consolidated Fire, fire hazard severity zones